PECO – Center Point Substation – 2011
Location: Landsdale, PA
The Center Point substation project in Lansdale, PA was awarded to Matrix NAC. The team worked 23,900 hours to complete the project for PECO which included the installation of the following:
• All underground conduits, ground grid and trench
• (3) 500kV breakers and (5) switches
• (3) 230kV breakers and (6) switches
The pre-manufactured control house and its internal wiring were also set-up by the team along with the power and control cable (86,500 LF and 2,640 terminations) and tertiary supports and bus.
23,900
hours to complete the project
3
500kV breakers and 5 switches
3
230kV breakers and 6 switches
Scope of Work
- Matrix NAC also installed the field steel supports,insulators, bus, CCVTs and LAs
- The pre-manufactured control house and its internal wiring were also set-up by the team along with the power and control cable (86,500 LF and 2,640 terminations) and tertiary supports and bus.