
PPL – Breinigsville Substation – 2011
Location: Breinigsville, Pennsylvania
Matrix NAC provided electrical construction services for the Breinigsville Substation project. The project was completed on schedule and budget with 30,000 man-hours worked and zero OSHA recordable incidents.
30K
man hours
4
500kV breakers and associated switches
0
OSHA recordable incidents
100%
on time and on budget
Scope of Work
- 500kV yard structures, equipment and bus including four 500kV breakers and associated switches
- 138/69kV yard structures, equipment and bus
- New control house, relays and yard cable
- All below grade grounding, conduit and trench work
- Site lighting
30K man hours, 0 recordables
Completed on time and on budget