UGI Energy Services Power Station
Location: Hunlock Creek, PA
Following an over-pressurization event, Matrix NAC evaluated and repaired Unit #6 Heat Recovery Steam Generator (HRSG).
Matrix NAC performed engineering with Stantec, project tracking, procurement, subcontracting, construction, and start-up. Matrix NAC completed the demolition and replacement to the majority of the boiler and Selective Catalytic Reduction (SCR) modules.
100%
commitment to quality delivery
0
incident safety culture
1986
the year we began offering union services
Scope of Work
- Provided engineering, procurement, and construction (EPC)
- Procured HRSG replacement modules from Victory
- Procured SCR modules